Street | Duration of work | Type | Description | Additional Information |
---|---|---|---|---|
Champlain | Extended to August 1 | Street closures | Water system replacement. | At the Lorette intersection |
Dieppe Blvd | July 7 to end of August | Lane reductions | Microsurfacing | Between Canaan and Melanson |
Street | Duration of work | Type | Description | Additional Information |
---|---|---|---|---|
Champlain |
July 21 to October | Lane reductions | Replacement of certain water mains and resurfacing work | Between Aviation and Lorette |
LeBlanc |
June 23 to end of August | Local traffic only | Reconstruction | N/A |
Ste-Thérèse |
June 16 to September | Local traffic only | Reconstruction | Between Paul and Acadie |
Copp |
June 2 to September | Local traffic only | Reconstruction | N/A |
Notre-Dame Thibodeau Latour Grand-Pré |
June 2 to August | Local traffic only | Watermain renewal | N/A |
Marché | May 26 to July | Possible short duration lane reductions | Construction of a walking and cycling trail | Between Amirault and Gauvin |
Gauvin | April 22 to August | Full closure | Reconstruction and addition of a walking and cycling trail | Between Marché and Acadie |